# Master BOQ - UAS Marquee — Islamabad

**Project**: UAS Marquee — Islamabad
**Client**: UAS Marquee (Private) Ltd, Islamabad
**Date**: 2026-08-02
**Total Items**: 32

## Trade Summary

| Trade | Amount (PKR) |
|---|---|
| Finishes | 126,423,400 |
| Electrical | 38,000,000 |
| Overhead & Profit (10%) | 34,468,857 |
| HVAC | 32,000,000 |
| PEB Steel | 23,085,000 |
| Preliminaries | 19,510,674 |
| Public Health | 14,000,000 |
| ELV | 12,000,000 |
| Boundary Wall | 12,000,000 |
| Reinforcement | 11,925,000 |
| Connections | 11,600,000 |
| Fire | 9,000,000 |
| Landscaping | 8,000,000 |
| RCC | 6,820,000 |
| Civil | 6,000,000 |
| Steel Fabrication | 5,265,000 |
| PCC | 3,230,000 |
| Gates | 3,000,000 |
| Brickwork | 1,969,920 |
| Plaster | 622,080 |
| Earthwork | 237,500 |

| **Sub Total** | **325,177,900** |
| Preliminaries (6%) | 19,510,674 |
| Overhead & Profit (10%) | 34,468,857 |
| **GRAND TOTAL** | **379,157,431** |

## Items

| Item | Qty | Unit | Rate (PKR) | Amount (PKR) | Trade |
|---|---|---|---|---|---|
| PEB MS Structure — perimeter columns (20) | 22,000 | kg | 285 | 6,270,000 | PEB Steel |
| PEB MS Structure — internal columns (4) | 9,000 | kg | 285 | 2,565,000 | PEB Steel |
| PEB MS Structure — radial rafters (20) | 30,000 | kg | 285 | 8,550,000 | PEB Steel |
| PEB MS Structure — apex ring + central mast | 12,000 | kg | 285 | 3,420,000 | PEB Steel |
| PEB MS Structure — glazed band mullions | 8,000 | kg | 285 | 2,280,000 | PEB Steel |
| Fabrication & Erection (all steel) | 81,000 | kg | 55 | 4,455,000 | Steel Fabrication |
| Surface Prep & Paint (all steel) | 81,000 | kg | 10 | 810,000 | Steel Fabrication |
| Base Plates 25mm | 12,000 | kg | 300 | 3,600,000 | Connections |
| Splice/Gusset 16mm | 18,000 | kg | 295 | 5,310,000 | Connections |
| Cleats 6mm | 6,000 | kg | 290 | 1,740,000 | Connections |
| Anchor / J-Bolts 25mm | 2,500 | kg | 380 | 950,000 | Connections |
| Excavation (25 footings + mast) | 950 | m3 | 250 | 237,500 | Earthwork |
| PCC 1:4:8 (footings blinding) | 380 | m3 | 8,500 | 3,230,000 | PCC |
| RCC 1:2:4 (footings + plinths) | 620 | m3 | 11,000 | 6,820,000 | RCC |
| Reinforcement Gr60 (footings/ring) | 45,000 | kg | 265 | 11,925,000 | Reinforcement |
| Brickwork 9in (base 0-10ft) | 5,184 | sft | 380 | 1,969,920 | Brickwork |
| Cement Plaster (internal base) | 5,184 | sft | 120 | 622,080 | Plaster |
| Glazed Band — double-glazed gold frame | 5,184 | sft | 4,200 | 21,772,800 | Finishes |
| Marble Flooring (premium) | 21,237 | sft | 3,800 | 80,700,600 | Finishes |
| False Ceiling + Conical Lining | 23,000 | sft | 650 | 14,950,000 | Finishes |
| Luxury Drapery & Trim | 1 | ls | 9,000,000 | 9,000,000 | Finishes |
| Electrical — transformer+gen+internal | 1 | ls | 38,000,000 | 38,000,000 | Electrical |
| HVAC — chillers+AHU+VRF | 1 | ls | 32,000,000 | 32,000,000 | HVAC |
| Public Health — water+plumbing | 1 | ls | 14,000,000 | 14,000,000 | Public Health |
| Fire Fighting — NFPA sprinkler+pumps | 1 | ls | 9,000,000 | 9,000,000 | Fire |
| ELV — CCTV+access+AV+BMS | 1 | ls | 12,000,000 | 12,000,000 | ELV |
| Boundary Wall & Fence | 1 | ls | 12,000,000 | 12,000,000 | Boundary Wall |
| Landscaping & Fountain Plaza | 1 | ls | 8,000,000 | 8,000,000 | Landscaping |
| Entrance Gates | 1 | ls | 3,000,000 | 3,000,000 | Gates |
| External Civil & Pavers | 1 | ls | 6,000,000 | 6,000,000 | Civil |
| Preliminaries & General (6%) | 1 | ls | 19,510,674 | 19,510,674 | Preliminaries |
| Overhead & Profit (10%) | 1 | ls | 34,468,857 | 34,468,857 | Overhead & Profit (10%) |